Limuru Road and UN Avenue Expansion on Course

Limuru Road
A section of Limuru road under expansion near the Village Market. (File image from Nation Media Group)

The expansion of Limuru Road and the UN Avenue into dual carriageways is at seven and eight percent respectively, with the two local contractors expected to complete the job by October next year.

The 3.2-kilometre Limuru Road phase I, which starts from Wangari Maathai Road junction to the Muthaiga Road junction, has been under construction since November 2022.

The 2.7 -kilometre UN Avenue road which starts from Limuru Road Junction to Northern bypass at Runda has also been under construction since November 2022.

The contract for the construction of the first phase of Limuru Road was awarded to Dero Construction at Sh1.6 billion last year.

A joint venture by Wak, Sajucy and Vaniax was awarded the Sh1.2 billion UN Avenue road contract. – Business Daily