The World Bank has warned that delays in compensating people affected by the construction of the 740km Isiolo–Mandera highway could expose the project to additional costs of approximately Sh1.2 billion every month.
In a letter addressed to the Kenyan government, World Bank Country Director Qimiao Fan said delays in acquiring possession of project sites had disrupted construction timelines across several sections of the Horn of Africa Gateway Development Project, raising the risk of significant cost overruns.
Fan said the additional monthly costs arise from supervision, security, site facilities, idle equipment and personnel, price escalation, and other time-related overheads. The project also faces additional expenses associated with the demobilisation and remobilisation of construction equipment.
According to the World Bank, compensation funds have been available since 2024, but the process did not begin until November 2025 and has so far been limited to the Isiolo–Modogashe section.
Of the 1,669 eligible project-affected persons identified along this section, 1,281 had been compensated at a cost of Sh456 million. The outstanding compensation process is expected to expose the section to additional costs of approximately Sh536 million per month.
The Wajir–Tarbaj–Kotulo section faces an estimated monthly exposure of Sh421 million, while the Kotulo–Kobo–Elwak section could incur an additional Sh243 million.
The National Land Commission, which is responsible for land valuation, is still identifying beneficiaries, with a significant portion of the affected land under communal ownership.
Fan urged the government to expedite the resolution of outstanding compensation issues to prevent further disruption to construction works.
The World Bank has committed $1.3 billion (approximately Sh168 billion) to the project, describing it as its largest investment in Kenya in a single project within one sector. Construction was reported to be approximately 60% complete, with completion targeted for June 2030. – Citizen